Data Center Zoning Moratorium
Context
Planning Board-sponsored articles define "data center," mark it not allowed in all districts, and add a moratorium until the 2028 annual town meeting to study districts, electrical supply, water, noise, air quality, stormwater, decommissioning, fiscal impact, and master plan consistency. Needs a two-thirds town meeting vote and state review. Likely future path: special permit. Part of the zoning articles on Special Town Meeting Warrant - October 19, 2026.
Status
Recommended to the October 19, 2026 Special Town Meeting.
Log
- 2026-10-07 - Planning Board Meeting — Public hearing; board voted to recommend the three articles; resident Michelle asked about process and voiced environmental concerns.