Heritage School MSBA Process
Context
The MSBA is to decide around December 9 whether to invite Heritage School into its program; the school must pick the grades to consider before October 2. Within 270 days of an invitation the town must form a building committee and fund a feasibility study (~$1M benchmark, range $750K-$2M), all of it Charlton borrowing (town ballot plus town meeting votes). Shepherd Hill/high school needs are anticipated later. Related: DCRSD $11.1M School Capital Request.
Status
Pending MSBA decision (~December 9, 2026).
Log
- 2026-09-16 - Finance Committee Meeting — Staff reported on that day's meeting with the school and MSBA about the pre-evaluation and timeline.