Griffin Road Waterline Extension
Context
The Griffin Road waterline extension was approved previously, but the Route 20 portion needs a MassDOT permit. Vinnie, Andrew Golas, and Nick Peele all lacked permissions to submit through the MassDOT portal; escalated to MassDOT and unresolved as of October 7. Work off Route 20 can proceed but the contractor should not dig the Route 20 section.
Status
Blocked on the MassDOT permit as of October 7, 2026.
Log
- 2026-10-07 - Water and Sewer Commission Meeting — MassDOT portal permissions still block the permit; Route 20 portion cannot start.
- 2026-09-02 - Water and Sewer Commission Meeting — Griffin Road waterline extension approved (from the existing video summary).
- 2026-08-05 - Water and Sewer Commission Meeting — Voted to waive tie-in fees for the privately funded Griffin Road water main extension (from the existing video summary).